Frequently asked questions
What investors, growers and consultants ask us before a project starts.
Project process
What does “turnkey” mean in your projects?
One contract and one responsible party for design, supply, construction, installation, commissioning and training. You receive a greenhouse that is ready to grow in, with a trained team and our agronomists present for the first crop. Single systems or a modernisation can also be contracted separately.
How long does a project take?
For a high-tech greenhouse of 5–10 hectares, 12–16 months from feasibility study to first harvest is typical. Utility connections, permitting and the construction season are the usual factors that lengthen or shorten that range. We issue a project-specific schedule with the proposal.
What do you need from us to start?
The location, the planned area and the crop are enough for a first conversation. For a feasibility study we also ask for a water analysis, information on gas and electricity connections, a site plan and your target market.
Who handles permits and local construction?
We prepare the technical documentation. Permit applications are normally submitted by the client or a locally licensed design office, because procedures differ by country. Civil works are carried out by local contractors under our supervision or by our own teams, depending on the project.
Technology
Glass or film: which do you recommend?
It depends on climate, crop and budget. Venlo glass gives the highest light transmission and the longest service life, and suits year-round fruiting vegetables in colder climates. Multi-span film costs less and performs well in warm, bright regions. We compare both on lifetime cost in the feasibility study.
Whose equipment do you use?
We specify equipment from established manufacturers, most of them European. In Azerbaijan the group is the official representative of 17 manufacturers, including Richel Group, Priva, Stolze, Netafim and Grodan, and our own 20-hectare greenhouse is where we prove systems before specifying them abroad. The final supplier list is agreed with the client for each project.
Can you cool a greenhouse in a desert climate?
Yes, within the limit set by wet-bulb temperature. In dry heat, pad-and-fan or a semi-closed design is usually sufficient. In humid coastal heat, mechanical cooling is added for part of the year. We size the system on hourly climate data for the site.
Do you design for water recirculation?
Yes, as standard for substrate crops. Drain water is collected, filtered, disinfected and reused, which typically saves 20–30% of water and 30–40% of fertiliser compared with free drainage. How long the loop can stay closed depends on the sodium content of the source water.
Commercial
How do you price a project?
In two steps. After the feasibility study you receive a budget estimate for the concept. A detailed quotation follows once the technical specification is agreed. We do not publish prices per square metre, because site, climate and technology level change them too much for a general figure to be useful.
Do you offer financing?
We are not a lender. Financing options and support schemes vary by country and by project, so we assess them case by case. We prepare the technical and budget documentation that banks, export credit agencies and development institutions normally ask for.
Do you guarantee yields?
No. Yield depends on the grower, the variety, the season and the market as much as on the greenhouse. We state typical ranges for comparable projects and say clearly that they are typical. Warranty terms for construction and equipment are set out in the contract.
Can we visit a reference site before deciding?
Our reference is the group’s own 20-hectare tomato complex in Zira, Baku, in operation since 2011. Contact us to discuss a visit and a meeting with the engineers and agronomists who would work on your project.
After handover
What support do you provide after handover?
Our agronomists accompany the first crop. After that, support continues under a service agreement: scheduled site visits, remote review of climate and irrigation data, and advice on crop strategy. The scope is agreed for each project.
How are spare parts and service organised?
At handover you receive as-built documentation, maintenance schedules and a recommended list of critical spare parts to keep on site. Further parts are supplied through us from the original manufacturers.
Will you train our staff?
Yes. Operators and growers are trained on their own systems during commissioning, and training continues through the first crop. Where it helps, part of the training can take place at our complex in Baku.
Can you manage the greenhouse for us?
Operation management is one of our services. The usual arrangement is an agreed period in which our specialists work alongside your team and hand over responsibility step by step. Scope and duration are defined in a separate agreement.
Still have a question?
Write to us. An engineer replies within two working days.
- Preliminary layout and budget range
- A visit to our 20-hectare reference greenhouse
- Support in English, Russian and Azerbaijani